Lloyds List:
Early oil flows from Russia's largest upstream projects in Sakhalin: Ian Craig,
chief executive of Sakhalin Energy Investment, explained why the budget
increased to $20bn.: Tuesday December 06, 2005
ExxonMobil sees production under way at Chayvo field and Shell tackles phase-two
challenges, writes Martyn Wingrove
RUSSIA's largest upstream projects in Sakhalin Island are making progress with
early oil flowing from both this quarter.
Oil majors ExxonMobil and Royal Dutch Shell are heavily investing in two large
oil and gas projects offshore eastern Russia, in harsh climates and remote
environments.
ExxonMobil is a leading partner in Sakhalin I, where early production from the
Chayvo oil and gas field is under way through the beach-based Yestreb (Hawk)
drilling rig and a leased processing system from Expro International.
Work on the first phase of developing three offshore fields in the Sakhalin I
production sharing agreement area is 70% complete with output of up to 50,000
barrels per day coming from the first key installation.
Work will continue into 2006 on construction of the main onshore processing
centre, near the Chayvo beach site, the 226 km export oil and gas pipelines and
the DeKastri export terminal on the Russian mainland.
'We have started limited production at Chayvo with a 50,000 barrel per day
leased production facility and are selling crude and gas to domestic customers,'
said Exxon Neftegas president Stephen Terni.
'Completion of the oil export system is expected mid-2006, with full field
production of 250,000 bpd expected by the end of next year.'
Exxon Neftegas anticipates producing from the southern part of Chayvo next year
using the Orlan offshore platform, which started drilling into the field last
week.
Orlan was upgraded from an Alaskan drilling platform and is a gravity-based
structure designed to operate in ice conditions.
Up to 20 extended reach wells could be drilled from Orlan into Chayvo, while
some of the wells drilled from Yastreb are the longest in the world.
'Extended reach drilling technology is cost-efficient and environmentally sound.
It reduced the capital and operating costs and reduced the environmental
impact,' Mr Terni told IBC Energy's Sakhalin Oil ' Gas Conference.
'All our project facilities are designed for severe sub-Arctic climate and
seismic conditions.
'The design codes were approved by the Russian regulatory agencies, which made
it possible to blend international technology with Russian standards.'
Exxon Neftegas operates the Sakhalin I project with a 30% interest. Its partners
are Russia state firm Rosneft, Oil ' Natural Gas Corp of India and Sodeco of
Japan.
The whole project includes developing 5bn barrels of oil and gas resources from
the Chayvo field, Arkutun-Dagi to the east and Odoptu to the north.
The complete project would have been a massive undertaking even for the oil
majors and other investors, so they progressed with Chayvo first.
'Because of the technical execution of the project in a challenging environment
we decided to go for a phased development to mitigate the risk and use the
lessons learnt on later phases,' said Mr Terni. 'We expect Odoptu to follow
Chayvo and Arkutun-Dagi to be developed later to maintain plateau production.'
Shell is a leading participant in Sakhalin Energy Investment, which has produced
oil from the Sakhalin II project since 1999 through the Vityaz production
complex.
This includes the Molikpaq production platform and Okha floating storage and
offloading vessel.
Work continues on the second phase of development within the Sakhalin II
production sharing agreement area with two platforms under construction for the
Piltun-Astokhskoye and Lunskoye fields.
Shell and its partners Mitsui and Mitsubishi have been forced to double the
budget on this project to $20bn due to a number of influences. Installation
problems with the onshore and offshore pipelines is a major part of the reason
for the year delay and cost overruns.
Ian Craig, chief executive of Sakhalin Energy Investment, explained why the
budget increased to $20bn.
'The challenging frontier, lengthening construction schedule, design
adjustments, some recommended from the Russian authorities, and oilfield
inflation of equipment and services made us increase the budget for work to
2014.'
Sakhalin II is now more than 60% completed, with the first milestones and
challenges overcome this year.
'The offshore concrete gravity base structures for the two platforms Piltun B
and Lunskoye A were installed as per the original schedule,' said Mr Craig.
'Work continues on the topsides in South Korea, with the Lunskoye topsides to be
loaded out next year and the Piltun structure in 2007.'
These platform topsides will be floated over the concrete bases and ballasted in
position in 2006 and 2007. They will be the largest structures in the world by
weight installed this way.
'Around 900 km of pipeline has been welded, so 60% of this has been completed,'
Mr Craig said.
'Construction of the liquefied natural gas terminal is ahead of schedule and
dredging of the channels are completed.'
Sakhalin Energy Investment expects all-year-round production from the project in
2008 and has already secured commitments for 75% of the LNG from the two trains
being built. It is looking into building another LNG train to export more of the
gas to Asian markets and US west coast. This is probably also part of the $20bn
budget.
Click here for ShellNews.net
HOME PAGE